Change orders for accounting engagements

What a change order records, when to use one on accounting file work, the fields it needs, and how approval works so a changed scope is paid and dated.

Country-neutral · Updated November 20, 2026

A change order is a short written amendment to a statement of work. It records that scope, time or fee has changed and that both sides agreed. It is the document that turns "can you also..." into a decision. This guide covers when to use one, what goes in it, and how to keep the process light enough that people actually follow it.

Country-neutral. The mechanism works in any country. Whether an amendment must take a particular form, and whether an email counts, depends on the governing law, so check your own regulator and have counsel adapt the wording. General information, not legal advice.

What a change order is, and is not

It is an amendment to your agreement with the firm: a record of an agreed change to the work you do for the firm.

It is not a change to the firm's engagement letter with its client. If the firm's engagement changes, the firm handles that with its client. Your change order only reflects what that change means for you.

It does not replace the master agreement. It refers to the statement of work it amends and leaves the standing terms in place.

When to use one

Use a change order whenever any of these changes after the SOW was signed.

  • Scope: added tasks, files, periods or deliverables; removed tasks.
  • Time: a new delivery date, whether because inputs were late or because the work grew.
  • Fee: any change in the fee, even when the scope is unchanged, such as a fee revised because the file turned out larger than described.
  • Standards or method: the firm changes the template or documentation requirement partway through.
  • Review rounds: the agreed number of review rounds is exceeded.

Do not use one for a correction of your own error. Fixing mistakes in your own deliverable is part of the original scope unless the agreement says otherwise.

The fields a change order needs

A useful change order fits on one page.

  1. Reference. The SOW or agreement it amends, its date, and a change number ("Change 1", "Change 2").
  2. Requested by and date. Who raised it and when.
  3. Description of the change. What is added, removed or altered, in the same units as the SOW.
  4. Reason. One line: late inputs, firm request, newly found issue.
  5. Effect on time. The new delivery date or the days added.
  6. Effect on fee. The added or reduced amount, and the basis. Rates and amounts are for you and the firm to agree; the form just records them.
  7. Effect on deliverables and standards. Anything that changes what you hand over or how it is measured.
  8. What does not change. A sentence stating that all other terms remain in force.
  9. Approval. Names, dates and signatures, or a stated electronic approval method.

Who approves

The person with authority to commit the firm to the change signs it. That may not be the person who sent the request. If a manager asks for extra work, ask whether they can approve the fee effect or whether it goes to someone else. Say so in the SOW: "changes are approved by the named contact or their delegate in writing".

For your side, the person bound by the agreement signs. If you contract through a company, the company signs.

Approval by email

Many small changes are agreed in email. If your agreement says changes may be approved by email from a named address, a short reply such as "Approved, as described in your message of the fifth" can work. Put that rule into the master agreement, because enforceability depends on the governing law and on what the agreement says. If in doubt, use the form.

Worked example (illustrative)

This is an invented example to show the arithmetic.

The SOW covers 5 reconciliations at 2 hours each: 5 x 2 = 10 hours, due on the tenth. The firm asks for 3 more reconciliations and a new due date of the fourteenth.

Added work: 3 x 2 = 6 hours. New total: 10 + 6 = 16 hours. The change order records: Change 1; adds 3 reconciliations; adds 6 hours; new due date the fourteenth; the fee effect is calculated on the same basis as the SOW (6 hours of the original 10-hour basis); all other terms unchanged. Both sides approve it before you start the extra reconciliations.

If the firm had added the 3 reconciliations but kept the tenth, the order would also need to say what happens to the date, or whether the work can be done in time at all. A change order that covers only one of scope, time and fee leaves the other two to dispute.

Habits that keep change orders working

  • Send it fast. Draft the change order the day the request comes in, while both sides remember the context.
  • One change, one order. Bundling several changes slows approval and muddles the record.
  • Keep numbering. A run of numbered change orders shows what happened to the job.
  • File them with the SOW. When someone later asks why the job took longer, the answer is in one folder.
  • Say what you do while waiting. Continue on the original scope. Start extra work only on approval.

Change orders and professional rules

Independence and confidentiality obligations do not pause when scope changes. If a change adds a new client or a new period, repeat your independence declaration for the added item if it concerns a different engagement. If it adds data, check that the confidentiality terms still cover it. For AICPA members, the AICPA Code of Professional Conduct sets these rules, in the Independence Rule (ET 1.200.001) and the Confidential Client Information Rule (ET 1.700.001); its current text is in the sources. Those who follow another regulator should read that regulator's rules.

Frequently asked questions

Is a change order the same as a new SOW?

No. A change order amends an existing SOW. A new SOW is a separate job. When changes pile up to the point that most of the original is replaced, a fresh SOW is cleaner.

Do I need one for every small change?

You need a record of every change that affects time, fee or deliverables. A one-line email confirmed by the firm can be that record if your agreement allows it.

What if the firm refuses to pay for a change?

Then the extra work should not start. If it already has, the record you kept of the request and your reply to it is what you will rely on. This is a contract question, and counsel in your jurisdiction can advise.

Can a change order reduce scope?

Yes. Removed tasks and a lower fee are recorded the same way.

Where do the official standards address this?

They address the firm's engagement with its client. For audits, AU-C section 210, Terms of Engagement, says the auditor should not agree to a change in the terms of the audit engagement when no reasonable justification for doing so exists (paragraph .17). The AICPA auditing standards in the sources have the current text. Changes between you and the firm are a matter of your contract.

Sources

Last verified November 20, 2026. Sources checked by the editorial team; not yet reviewed by a named professional. General information, not legal, tax or accounting advice.

Related pages

Terms used on this page

Statement of work, Change order

Join the CORAA CPA network waitlist

CORAA prepares audit files for US CPA firms. Network members are independent contractors who clear what the software flags, with evidence and a note, paid per file under a contractor agreement.

  • Files are offered to you; you accept or decline
  • No exclusivity: you can work for others
  • The firm reviews and signs; CORAA never does

* required