The formulas
- Progress = (costs incurred - materials) / (total costs - materials)
- Revenue = progress x (price - materials) + materials
How it works
ASC 606-10-55-21(b) adjusts a cost-based input method when a cost is not proportionate to progress. Revenue on such a good is recognized at its cost when the good is not distinct, the customer is expected to obtain control of it significantly before receiving services related to it, the cost is significant to the total, and the entity procures it from a supplier without significant involvement in designing or manufacturing it.
The example uses the figures in ASC 606-10-55-187 to 55-192: a $5 million refurbishment with $1.5 million of elevators gives 20 percent progress and $2.2 million of revenue.
Illustrative figures only. Check the result against your firm's methodology before relying on it.
Common questions
Why zero margin on the materials?
Margin on goods procured and passed through would overstate performance. The margin is earned on the remaining work.
Do wasted materials count as progress?
No. ASC 606-10-55-21(a) excludes costs of significant inefficiencies not reflected in the price.
What happens after installation?
The materials cost stays out of the measure of progress and the revenue on them stays equal to their cost. The margin is earned only on the remaining work.
Sources
Runs in your browser. The figures you type are not sent to CORAA or stored. Check the result against your firm's methodology before relying on it.