The formulas
- Earned hours = budget x percent complete
- Efficiency = earned hours / actual hours
- Estimate at completion = actual hours / percent complete
- Projected overrun = estimate at completion - budget
How it works
Percent complete is a judgment, so set it by deliverables finished and not by hours used. The projection assumes the rest of the work runs at the efficiency seen so far.
Illustrative figures only. Check the result against your firm's methodology before relying on it.
Common questions
What if percent complete is understated?
The estimate at completion rises. Review the percent first when a projection looks wrong.
Is a variance always bad?
A variance after a scope change or a late client file reflects the change. Record the reason with it.
Formulas on this page are the standard definitions.