Construction Job Cost Cutoff and Accrual Test

For a contractor, a missed invoice is more than an unrecorded liability. It lowers cost to date, understates percent complete and moves revenue and gross profit.

Standard
ASC 606-10-55-20 / AU-C 330
Format
Excel (.xlsx)
Cost
Free
Access
No sign-up

What it is

For a contractor, a missed invoice is more than an unrecorded liability. It lowers cost to date, understates percent complete and moves revenue and gross profit.

The workbook tests invoices against the date work was performed, flags unrecorded and early costs, and calculates the effect on cost to date, percent complete, revenue and gross profit by job.

When to use it

What’s inside

Standard cited

This template follows ASC 606-10-55-20 / AU-C 330. It is written in our own words, except for phrases the standard requires the document to contain, with [bracketed placeholders] for client details, amounts in USD and dates as MM/DD/YYYY. Check it against the current standard and your firm’s methodology before use. See AU-C 330 explained.

Download free Excel template (.xlsx)

Questions

Which date matters?

The date the work was performed or delivered, not the invoice date.

Does it update the estimate to complete?

No. If unrecorded costs show the estimate is low, update it before relying on the revenue effect.