Construction Job Cost and Percent Complete Audit Program

In a contractor audit the estimate at completion drives profit. A small change in the estimated cost to finish a job moves revenue and gross profit in the period.

Standard
ASC 606 / AU-C 330, 540
Format
Word (.docx)
Cost
Free
Access
No sign-up

What it is

In a contractor audit the estimate at completion drives profit. A small change in the estimated cost to finish a job moves revenue and gross profit in the period.

The program covers the WIP schedule, estimates at completion, job cost and cutoff, change orders and claims, and presentation of contract assets and liabilities.

When to use it

What’s inside

Standard cited

This template follows ASC 606 / AU-C 330, 540. It is written in our own words, except for phrases the standard requires the document to contain, with [bracketed placeholders] for client details, amounts in USD and dates as MM/DD/YYYY. Check it against the current standard and your firm’s methodology before use. See AU-C 330 explained.

Download free Word template (.docx)

Questions

Which progress method does it assume?

An input method such as cost to cost (606-10-55-20), with attention to inputs that do not depict transfer of control (606-10-55-21). Output methods need their own procedures.

Is there a cutoff schedule?

Yes. The job cost cutoff and accrual test shows the effect on percent complete, revenue and gross profit.