- Apply the three criteria in 606-10-25-27 to decide whether an obligation is satisfied over time
- Use the control indicators to find the point in time for other obligations
- Select an output or input method and exclude costs that do not depict transfer
- Apply the right-to-invoice practical expedient
Control is the test
Revenue is recognized when (or as) the entity satisfies a performance obligation by transferring control of a good or service (606-10-25-23). Control is the ability to direct the use of, and obtain substantially all of the remaining benefits from, the asset. For each obligation, the entity decides at contract inception whether it is satisfied over time; if not, it is satisfied at a point in time (606-10-25-24).
The three over-time criteria
Under 606-10-25-27, an obligation is satisfied over time if any one of these is met:
- The customer simultaneously receives and consumes the benefits as the entity performs. Routine recurring services such as cleaning or payroll processing.
- The entity's performance creates or enhances an asset the customer controls as it is created. Construction on the customer's land is the common example.
- The performance does not create an asset with an alternative use to the entity, and the entity has an enforceable right to payment for performance completed to date.
Criterion 3 has two parts. Alternative use is assessed at inception and considers contractual restrictions and practical limitations (606-10-25-28), such as significant rework cost to redirect a custom item. The right to payment must be an amount that approximates the selling price of the work completed to date (for example, costs incurred plus a reasonable margin), not just compensation for lost profit, if the customer terminates for reasons other than the entity's failure to perform. It must also be enforceable under the contract and the law of the jurisdiction. Read the termination clause and, if needed, get legal input.
Point-in-time indicators
If no criterion is met, the entity determines the point at which control transfers. 606-10-25-30 lists indicators:
- the entity has a present right to payment;
- the customer has legal title;
- the entity has transferred physical possession;
- the customer has the significant risks and rewards of ownership; and
- the customer has accepted the asset.
No single indicator decides the answer. Shipping terms matter: under shipping-point terms, control often transfers at shipment; under destination terms, at delivery. Bill-and-hold, consignment and repurchase arrangements have their own guidance, covered in lesson 13.
Measuring progress
For each over-time obligation, the entity uses a single method of measuring progress and applies it consistently to similar obligations, remeasuring at each reporting date (606-10-25-31 and 25-32). Changes in the measure are changes in accounting estimate (606-10-25-35).
- Output methods measure value transferred: surveys of performance, milestones reached, units delivered, time elapsed. They are direct, but units-delivered can misstate progress when work in process the customer controls is material.
- Input methods measure effort: costs incurred, labor hours, machine hours, resources consumed. Cost-to-cost is common in construction.
Under 606-10-25-34, exclude from the measure goods or services that do not transfer control, and include those that do. Two adjustments matter for input methods:
- Costs that do not reflect performance, such as wasted materials or rework from inefficiency not priced into the contract, are excluded from cost incurred.
- Uninstalled materials that are not distinct, transfer to the customer before installation, are significant relative to total costs and are procured from a third party without significant design involvement are recognized at cost (zero margin) rather than included in progress.
If the entity cannot reasonably measure the outcome but expects to recover its costs, it recognizes revenue to the extent of costs incurred until it can.
Right-to-invoice practical expedient
Under 606-10-55-18, if the entity's right to consideration corresponds directly with the value to the customer of performance completed to date, such as a fixed hourly rate, it may recognize revenue in the amount it has a right to invoice. A large upfront or back-end payment that does not track value disqualifies it.
See the percentage of completion calculator and the uninstalled materials calculator.
Cost-to-cost with uninstalled elevators
Pinecrest Builders contracts to renovate a building on the customer's land for $5,000,000. Expected total costs are $4,000,000, including elevators bought from a manufacturer for $1,200,000. Pinecrest performs the work on an asset the customer controls (criterion 2), so the obligation is satisfied over time. It uses cost-to-cost.
At year-end, costs incurred are $2,000,000, including the $1,200,000 elevators, delivered and controlled by the customer but not yet installed. The elevators are not distinct, are significant, and Pinecrest has no design role in them.
Adjusted measure: exclude elevators from both numerator and denominator. Progress = (2,000,000 minus 1,200,000) / (4,000,000 minus 1,200,000) = 800,000 / 2,800,000 = 28.6 percent.
Revenue: elevators at cost $1,200,000 plus (800,000 / 2,800,000) x (5,000,000 minus 1,200,000) = 28.571 percent x 3,800,000 = $1,085,714. Total $2,285,714.
Without the adjustment, progress would be 50 percent and revenue $2,500,000, overstating revenue by about $214,000 by earning margin on purchased elevators.
Self-check
Answer each question before you open the answer.
List the three over-time criteria.
Show answer
The customer simultaneously receives and consumes the benefits as the entity performs; performance creates or enhances an asset the customer controls; or performance creates no asset with an alternative use and the entity has an enforceable right to payment for performance to date.
Is legal title transfer enough by itself to conclude control has passed?
Show answer
No. It is one of several indicators in 606-10-25-30 (present right to payment, legal title, physical possession, significant risks and rewards, customer acceptance), weighed together.
How are significant uninstalled materials procured from a third party handled in a cost-to-cost measure?
Show answer
When the conditions are met, they are excluded from the measure of progress and revenue is recognized equal to their cost (zero margin) when control transfers.
When can the right-to-invoice practical expedient be used?
Show answer
When the entity's right to consideration corresponds directly with the value to the customer of performance completed to date, such as a fixed rate per hour of service.
Use it on the file
- ToolPercentage of Completion Calculator (Cost-to-Cost, ASC 606)
- ToolASC 606 Input Method with Uninstalled Materials (Revenue at Cost)
- GuideConstruction Contractor Audits: Percentage of Completion, WIP Schedules and Surety
- ToolASC 606 Output Method Progress Calculator with Cumulative Catch-Up
Sources
Standards are paraphrased from the primary sources listed above; read the source before relying on a requirement. This lesson is training material, not professional advice. Report an error